Two-week look-ahead
Harbor Point Apartments · Nov 2–13, 2026 · Fictional schedule
GUIDED SCENARIO · SCHEDULE INTELLIGENCE
Schedule delay and critical-path impact
BEFORE · FICTIONAL RECORDS
Look-ahead looks normal
Exterior windows · east: Nov 5–10 with 2 days of float.
Submittal 08-001 (window shop drawings) is needed back Nov 3; the architect now forecasts Nov 8.
- Exterior windows · east
- East dry-in milestone
- L2 drywall hang
- 08-001
STEP 1 OF 3 · AI
Real GenStruc AI feature · sample outputDelay found: east windows
Impact
Submittal 08-001 is forecast 5 days late (Nov 3 → Nov 8), so the exterior windows · east finish moves from Nov 10 to Nov 15.
Its 2 days of float absorb part of the slip. The east dry-in milestone moves 3 days (Nov 12 → Nov 15), and L2 drywall hang, on the critical path, starts Nov 16 instead of Nov 13.
Evidence
08-001 forecast Nov 8 · Exterior windows · east float 2 d · L2 drywall hang float 0 d.
STEP 2 OF 3 · AI
Real GenStruc AI feature · sample outputRecovery options for the team
Option 1
Ask the architect for a partial return on the east-elevation units by Nov 4. One day late stays inside the 2 days of float, so the milestone holds.
Option 2
Start L2 drywall on the west side first, where the east windows do not hold the work.
Not changed
AI does not change dates or notify anyone.
STEP 3 OF 3 · PROJECT MANAGER
Your team’s decision · illustrativeTeam chooses option 1
The scheduler updates dates only after the architect confirms.
| Activity | If partial return arrives Nov 4 | Without action |
|---|---|---|
| Exterior windows · east | Finish Nov 11 (1 day of float used) | Finish Nov 15 |
| East dry-in milestone | Nov 12 · holds | Nov 15 · +3 days |
| L2 drywall hang | Start Nov 13 · holds | Start Nov 16 · +3 days |
Result
A 3-day critical-path slip is caught on Nov 2, with a recovery path chosen while there is still float to use.
Scripted sample: prewritten from this demo’s fictional records. No AI runs on these pages, and nothing is saved or sent. Labels: Real GenStruc AI feature · sample output / Your team’s decision · illustrative.
GUIDED SCENARIO · AI LOOK-AHEAD PLANNER
Build a two-week look-ahead
BEFORE · FICTIONAL RECORDS
Schedule window: Nov 2–13
Six activities, two predecessor holds and one open submittal.
- L2 slab inspection
- L2 framing
- MEP rough-in · L1
- Exterior windows · east
- 08-001
STEP 1 OF 1 · AI
Real GenStruc AI feature · sample outputTwo-week look-ahead · Nov 2–13
| Start | Activity | Crew | Ready? |
|---|---|---|---|
| Nov 2 | L2 slab inspection | Field team | Ready |
| Nov 3 | L2 framing | Carpentry | Hold · needs slab inspection |
| Nov 4 | MEP rough-in · L1 | MEP trades | Ready · 25% complete |
| Nov 5 | Exterior windows · east | Envelope | Hold · submittal 08-001 |
| Nov 12 | East dry-in milestone | Envelope | At risk · follows windows |
| Nov 13 | L2 drywall hang | Drywall | At risk · follows dry-in |
Summary
2 ready · 2 on hold · 2 at risk. A superintendent confirms crews before it is shared.
Result
The superintendent gets a ready/hold list for the next two weeks in seconds, instead of rebuilding it by hand.
Related:Schedule risk
Scripted sample: prewritten from this demo’s fictional records. No AI runs on these pages, and nothing is saved or sent. Labels: Real GenStruc AI feature · sample output.
Schedule & look-ahead
Fictional records| Activity | Start | Finish | Float | Progress | Responsible |
|---|---|---|---|---|---|
| L2 slab inspection | Nov 2 | Nov 2 | 0 d · critical | 0% · Scheduled | Field team |
| L2 framing | Nov 3 | Nov 6 | 0 d · critical | 0% · Awaiting predecessor | Carpentry |
| MEP rough-in · L1 | Nov 4 | Nov 13 | 6 d | 25% · In progress | MEP trades |
| Exterior windows · east | Nov 5 | Nov 10 | 2 d | 0% · At risk | Envelope |
| East dry-in milestone | Nov 12 | Nov 12 | 0 d · milestone | Not reached | Envelope |
| L2 drywall hang | Nov 13 | Nov 20 | 0 d · critical | 0% · Not started | Drywall |
SELECTED CONTEXT
Exterior windows · east
Predecessor: opening verification.
Constraint: window shop drawing response (submittal 08-001).
Successors: east dry-in milestone, then L2 drywall hang.
Review related submittalYOUR NEXT STEP