COMMERCIAL & MULTIFAMILY
Your project. Every moving part.
PROJECT WORKSPACE / 03
Budget, GMP & buyout savings
Harbor Point Apartments · Fixed GMP contract · Every figure is fictional
All numbers are fictional. Scripted changes on this screen are demo simulations, not AI or live automation, and nothing is saved, approved or paid. In GenStruc today: Budget tabs for GMP, Buyout Tracker, Change Orders and Financial Reports; Current GMP = original GMP + approved owner change orders; subcontractor change requests never change the GMP; change-order approval limits per person. Not in GenStruc today: recording executed subcontract awards and tracking buyout savings realized, used and remaining. Those parts are labeled Demo only.
GUIDED SCENARIO · FIXED-GMP SAVINGS TRACKING
Buyout savings: realized, used and remaining
BEFORE · FICTIONAL RECORDS
At GMP signing · estimate only
Original GMP $28,400,000 · fixed. Initial estimated cost $26,000,000 (trade packages plus general conditions).
Projected gross margin $2,400,000 = GMP − estimated cost (fee and contingency). No trades are awarded, so there are no savings yet.
- 03 · Concrete & sitework
- 09 · Interiors & finishes
- BIDS-09
- SCO-LOG
- COST-LOG
- CO-004
STEP 1 OF 6 · PROJECT MANAGER · JORDAN ELLIS
Demo only · not available in GenStruc todayBuyout: $500,000 realized savings
Five signed awards came in below their budgets. Interiors is still out to bid: the $90,000 gap to the low bid is not counted, and that trade stays forecast at budget.
GenStruc does not record executed awards or track savings today; this step is shown for illustration only.
Arbor Interiors · $4,610,000 · bid, not awarded
Keystone Finishes · $4,735,000 · bid, not awarded
| Figure | Before | After | Change |
|---|---|---|---|
| Realized buyout savings | $0 | $500,000 | +$500,000 |
| Savings remaining | $0 | $500,000 | +$500,000 |
| Projected final cost | $26,000,000 | $25,500,000 | −$500,000 |
| Projected gross margin | $2,400,000 | $2,900,000 | +$500,000 |
| Original GMP (fixed) | $28,400,000 | $28,400,000 | No change |
STEP 2 OF 6 · PROJECT MANAGER · JORDAN ELLIS
Demo simulation · scripted, fictional numbers · not AISubcontract cost change orders use $175,000
These are cost changes with subcontractors, not owner change orders. They raise projected cost and use savings; the GMP stays fixed.
SCO-01 · Bayline Concrete · Added rebar at L2 transfer slab (coordination gap) · $110,000
SCO-02 · Coastal MEP Partners · Relocated plumbing riser at existing utility (field condition) · $65,000
| Figure | Before | After | Change |
|---|---|---|---|
| Savings used | $0 | $175,000 | +$175,000 |
| Savings remaining | $500,000 | $325,000 | −$175,000 |
| Projected final cost | $25,500,000 | $25,675,000 | +$175,000 |
| Projected gross margin | $2,900,000 | $2,725,000 | −$175,000 |
| Original GMP (fixed) | $28,400,000 | $28,400,000 | No change |
STEP 3 OF 6 · PROJECT MANAGER · JORDAN ELLIS
Demo simulation · scripted, fictional numbers · not AIOther overruns use $75,000 more
Savings used now total $250,000 ($175,000 subcontract COs + $75,000 other overruns), leaving $250,000.
Using savings is a tracking view your team controls. Nothing is transferred automatically, and savings are never moved into contingency.
OC-01 · Tower crane rental extended 3 weeks · General conditions · $45,000
OC-02 · Winter protection and temporary heat · Self-performed work · $30,000
| Figure | Before | After | Change |
|---|---|---|---|
| Savings used | $175,000 | $250,000 | +$75,000 |
| Savings remaining | $325,000 | $250,000 | −$75,000 |
| Projected final cost | $25,675,000 | $25,750,000 | +$75,000 |
| Projected gross margin | $2,725,000 | $2,650,000 | −$75,000 |
| Original GMP (fixed) | $28,400,000 | $28,400,000 | No change |
STEP 4 OF 6 · PROJECT ENGINEER · PRIYA SHAH
GenStruc workflow · sample records · not AISomeone tries to bill SCO-01 to the owner
Refused: subcontract cost changes never change the GMP. Only owner-approved change orders do.
STEP 5 OF 6 · PROJECT MANAGER · JORDAN ELLIS
Demo simulation · scripted, fictional numbers · not AIOwner approves CO-004 · separate from savings
The owner pays for the added scope, so revised GMP and projected cost rise by the same amount. Original GMP, margin and savings do not move.
In GenStruc, approving an owner change order updates Current GMP once.
Handrail embed plates at L2 stair core · Design revision · +$38,600 · 0 days (fabricated off the critical path).
Owner-requested scope after the structural engineer’s answer. Owner change orders are kept separate from subcontract cost changes.
| Figure | Before | After | Change |
|---|---|---|---|
| Original GMP (fixed) | $28,400,000 | $28,400,000 | No change |
| Revised GMP | $28,400,000 | $28,438,600 | +$38,600 |
| Projected final cost | $25,750,000 | $25,788,600 | +$38,600 |
| Projected gross margin | $2,650,000 | $2,650,000 | No change |
| Realized buyout savings | $500,000 | $500,000 | No change |
| Savings remaining | $250,000 | $250,000 | No change |
Allowed: within Jordan’s approval limit ($50,000 · sample), with the owner’s signed approval attached (sample).
STEP 6 OF 6 · DEMO SUMMARY
Demo simulation · scripted, fictional numbers · not AITotals reconcile · nothing counted twice
Margin is a projection, not realized profit, and is shown before any owner share of savings. Savings-sharing clauses or contingency terms in your contract may change how much is available.
| Check | Calculation | Result |
|---|---|---|
| Savings remaining | $500,000 realized − $250,000 used | $250,000 |
| Projected final cost | $26,000,000 estimate − $500,000 savings + $250,000 used + $38,600 owner scope | $25,788,600 |
| Same cost, built from records | $19,275,000 awarded + $4,700,000 not awarded + $38,600 owner scope + $1,775,000 general conditions and other costs | $25,788,600 |
| Revised GMP | $28,400,000 original (fixed) + $38,600 approved owner COs | $28,438,600 |
| Projected gross margin | $28,438,600 − $25,788,600 | $2,650,000 |
Result
Buyout realized $500,000; subcontract COs and other overruns used $250,000; $250,000 remains. The original GMP stayed at $28,400,000 throughout. Every figure is fictional.
Scripted sample: prewritten from this demo’s fictional records. No AI runs on these pages, and nothing is saved or sent. Labels: Demo only · not available in GenStruc today / Demo simulation · scripted, fictional numbers · not AI / GenStruc workflow · sample records · not AI.
Budget & Financials
Fictional records| Trade package | Budget | Award | Subcontract COs | Status | Buyout savings |
|---|---|---|---|---|---|
| 03 · Concrete & sitework | $4,900,000 | $4,780,000 | +$110,000 | Awarded · Bayline Concrete | $120,000 realized |
| 06 · Framing & carpentry | $3,700,000 | $3,640,000 | — | Awarded · Tidewater Framing | $60,000 realized |
| 07 · Roofing & waterproofing | $1,500,000 | $1,420,000 | — | Awarded · Summit Roofing | $80,000 realized |
| 08 · Windows & glazing | $2,100,000 | $1,968,000 | — | Awarded · Clearline Glazing | $132,000 realized |
| 09 · Interiors & finishes | $4,700,000 | — | — | Not awarded · forecast at budget | Not counted until awarded |
| 22–26 · Mechanical, plumbing & electrical | $7,400,000 | $7,292,000 | +$65,000 | Awarded · Coastal MEP Partners | $108,000 realized |
SELECTED CONTEXT
How buyout savings are counted here
Realized savings come only from signed awards below their trade budget. Trades not yet awarded stay at budget, and pending bids never count.
Subcontract cost change orders and other overruns use up savings first. They raise projected cost but never change the GMP.
Savings remaining are not profit. Savings-sharing clauses or contingency terms in your contract may change how much is available.
Walk through savings realized, used and remainingBuyout savings · realized, used, remaining
| Item | Type | Amount |
|---|---|---|
| 03 · Concrete & sitework · Bayline Concrete | Realized · signed award vs budget | $120,000 |
| 06 · Framing & carpentry · Tidewater Framing | Realized · signed award vs budget | $60,000 |
| 07 · Roofing & waterproofing · Summit Roofing | Realized · signed award vs budget | $80,000 |
| 08 · Windows & glazing · Clearline Glazing | Realized · signed award vs budget | $132,000 |
| 22–26 · Mechanical, plumbing & electrical · Coastal MEP Partners | Realized · signed award vs budget | $108,000 |
| Realized buyout savings | Signed awards only | $500,000 |
| SCO-01 · Bayline Concrete · Added rebar at L2 transfer slab (coordination gap) | Used · subcontract cost CO | −$110,000 |
| SCO-02 · Coastal MEP Partners · Relocated plumbing riser at existing utility (field condition) | Used · subcontract cost CO | −$65,000 |
| OC-01 · Tower crane rental extended 3 weeks | Used · general conditions overrun | −$45,000 |
| OC-02 · Winter protection and temporary heat | Used · self-performed work overrun | −$30,000 |
| Savings used | Subcontract COs + other overruns | −$250,000 |
| Savings remaining | Unallocated · not profit | $250,000 |
Not counted as savings: 09 Interiors & finishes, still out to bid and forecast at its $4,700,000 budget. The $90,000 gap to the low bid counts only once a subcontract is signed. Savings-sharing clauses or contingency terms in your contract may change how much is available. Nothing is transferred automatically.
GMP · original stays fixed
| Item | Status | Amount |
|---|---|---|
| Original GMP · signed contract | Fixed | $28,400,000 |
| Approved owner change orders | None approved yet | $0 |
| Revised GMP | Original + approved owner COs only | $28,400,000 |
Not in the GMP: pending owner change orders ($224,600, exposure only), rejected ones ($212,000, no effect) and all subcontract cost change orders.
Change orders · kept in two separate logs
Owner change orders · change the GMP once approved
| Number | Description | Source | Value | Schedule | Status | Effect |
|---|---|---|---|---|---|---|
| CO-001 | Upgraded lobby finishes | Owner directive | +$186,000 | 0 days | Pending | Exposure only · not in GMP |
| CO-004 | Handrail embed plates at L2 stair core | Design revision | +$38,600 | 0 days | Pending | Exposure only · not in GMP |
| PCO-005 | EV charging stations in garage | Owner request | +$212,000 | +3 days | Rejected | No effect |
Subcontract cost change orders · change cost only, never the GMP
| Number | Subcontractor | Description | Cost | Status | Effect |
|---|---|---|---|---|---|
| SCO-01 | Bayline Concrete | Added rebar at L2 transfer slab (coordination gap) | +$110,000 | Approved | Uses buyout savings · GMP unchanged |
| SCO-02 | Coastal MEP Partners | Relocated plumbing riser at existing utility (field condition) | +$65,000 | Approved | Uses buyout savings · GMP unchanged |
Projected final cost & gross margin
| Line | Amount |
|---|---|
| Initial estimated cost · trades $24,300,000 + general conditions $1,700,000 | $26,000,000 |
| Less realized buyout savings | −$500,000 |
| Plus subcontract cost change orders | +$175,000 |
| Plus other overruns | +$75,000 |
| Plus approved owner change-order scope | $0 |
| Projected final cost | $25,750,000 |
| Check · awarded $19,275,000 + not awarded $4,700,000 + general conditions and other costs $1,775,000 + owner scope $0 | $25,750,000 |
| Revised GMP | $28,400,000 |
| Projected gross margin · was $2,400,000 at signing | $2,650,000 |
Each dollar is counted once: savings already lower the cost, and change orders and overruns raise it. Margin includes the fee ($1,500,000) and unused contingency ($900,000). It is a projection, not realized profit, shown before any owner share of savings. GenStruc’s live Financial Reports stay more conservative and do not count savings until signed-award records are available.
YOUR NEXT STEP