SINGLE-FAMILY HOMEBUILDING

Build one home. See the whole picture.

FICTIONAL DEMO · NOTHING SAVED
Cedar Grove / Lot 12 / AspenAM

HOME WORKSPACE / 02

Lot 12 · Home schedule

128 Willow Lane · Aspen · Start / Complete workflow

Demo

Sample records only: pressing the buttons below changes nothing.

Started task1Fictional status
Upcoming tasks4In order
Automatic approvals0Explicit review

GUIDED SCENARIO · SCHEDULE RISK + RECOVERY PLAN DRAFT

Task delay, downstream impact and recovery

5 actions

BEFORE · FICTIONAL RECORDS

Lot 12 schedule on Monday

Sheathing started Nov 2 and should complete Nov 3. Strapping, its inspection, Dry-In and Plumbing Rough follow in order.

  • Wall / Roof Sheathing
  • Strapping
  • Strapping inspection
  • Wall / Roof Dry-In
  • Plumbing Rough / Tubset

STEP 1 OF 5 · SUPERINTENDENT · ALEX MORGAN

GenStruc workflow · sample records · not AI

Superintendent marks Sheathing blocked

Wall / Roof Sheathing · Blocked Nov 3, 10:30 am · reason: rain, and OSB delivery short 40 sheets. Expected to resume Nov 4.

Allowed: Superintendent assigned to this home. Purchasing cannot change task status.

STEP 2 OF 5 · SCHEDULE RULES

GenStruc workflow · sample records · not AI

Downstream dates · proposed, not applied

Calculated from the task order and durations. Live dates change only after a manager accepts.

Downstream dates · proposed, not applied
TaskWasProposedChange
Wall / Roof SheathingFinish Nov 3Finish Nov 5+2 workdays
StrappingNov 4Nov 6+2
Strapping inspectionNov 5Nov 9+2
Wall / Roof Dry-InNov 6–9Nov 10–11+2
Plumbing Rough / TubsetNov 10–11Nov 12–13+2

STEP 3 OF 5 · AI

Homebuilding AI · in development, not yet verified · sample output

Proposed recovery plan

Option

Start Plumbing Rough / Tubset on interior walls alongside Dry-In (start-to-start), Nov 11 instead of Nov 12. Recovers 1 workday.

Requires confirmation

Plumber availability on Nov 11. No overtime or extra crews are assumed.

Not changed

Nothing has been changed. A manager must review and accept any date change.

STEP 4 OF 5 · CONSTRUCTION MANAGER

GenStruc workflow · sample records · not AI

Manager accepts the new dates

Proposal accepted. The original dates are kept in the revision history with who accepted the change and when.

The recovery option stays pending until the plumber confirms.

STEP 5 OF 5 · AI

Homebuilding AI · in development, not yet verified · sample output

2-week look-ahead · Lot 12

2-week look-ahead · Lot 12
DateTaskTradeNote
Nov 4–5Wall / Roof SheathingFramingResume when OSB arrives Wed
Nov 6StrappingFramingReady after sheathing
Nov 9Strapping inspectionInspectorRequest now
Nov 10–11Wall / Roof Dry-InRoofingAfter inspection passes
Nov 12–13Plumbing Rough / TubsetPlumbingNov 11 start if confirmed
Result

A 2-day weather delay is pushed through the whole home schedule, with a recovery option and an updated look-ahead, before trades show up on the wrong day.

Related:Strapping inspection

Scripted sample: prewritten from this demo’s fictional records. No AI runs on these pages, and nothing is saved or sent. Labels: GenStruc workflow · sample records · not AI / Homebuilding AI · in development, not yet verified · sample output.

Home schedule

Fictional records
Lot 12 · Home schedule fictional data
TaskTradePlannedStartCompleteStatus
Wall / Roof SheathingFramingNov 2–3Nov 2—Started
StrappingFramingNov 4——Not started
Strapping inspectionInspectorNov 5——Scheduled
Wall / Roof Dry-InRoofingNov 6–9——Not started
Plumbing Rough / TubsetPlumbingNov 10–11——Not started

SELECTED CONTEXT

Wall / Roof Sheathing

Assigned trade: framing · Fictional assignment.

Example Start: Nov 2 · completion not yet recorded.

Milestone completion is not an inspection pass or occupancy approval.

Walk through a delay