Lot 12 · Home schedule
128 Willow Lane · Aspen · Start / Complete workflow
Sample records only: pressing the buttons below changes nothing.
GUIDED SCENARIO · SCHEDULE RISK + RECOVERY PLAN DRAFT
Task delay, downstream impact and recovery
BEFORE · FICTIONAL RECORDS
Lot 12 schedule on Monday
Sheathing started Nov 2 and should complete Nov 3. Strapping, its inspection, Dry-In and Plumbing Rough follow in order.
- Wall / Roof Sheathing
- Strapping
- Strapping inspection
- Wall / Roof Dry-In
- Plumbing Rough / Tubset
STEP 1 OF 5 · SUPERINTENDENT · ALEX MORGAN
GenStruc workflow · sample records · not AISuperintendent marks Sheathing blocked
Wall / Roof Sheathing · Blocked Nov 3, 10:30 am · reason: rain, and OSB delivery short 40 sheets. Expected to resume Nov 4.
Allowed: Superintendent assigned to this home. Purchasing cannot change task status.
STEP 2 OF 5 · SCHEDULE RULES
GenStruc workflow · sample records · not AIDownstream dates · proposed, not applied
Calculated from the task order and durations. Live dates change only after a manager accepts.
| Task | Was | Proposed | Change |
|---|---|---|---|
| Wall / Roof Sheathing | Finish Nov 3 | Finish Nov 5 | +2 workdays |
| Strapping | Nov 4 | Nov 6 | +2 |
| Strapping inspection | Nov 5 | Nov 9 | +2 |
| Wall / Roof Dry-In | Nov 6–9 | Nov 10–11 | +2 |
| Plumbing Rough / Tubset | Nov 10–11 | Nov 12–13 | +2 |
STEP 3 OF 5 · AI
Homebuilding AI · in development, not yet verified · sample outputProposed recovery plan
Option
Start Plumbing Rough / Tubset on interior walls alongside Dry-In (start-to-start), Nov 11 instead of Nov 12. Recovers 1 workday.
Requires confirmation
Plumber availability on Nov 11. No overtime or extra crews are assumed.
Not changed
Nothing has been changed. A manager must review and accept any date change.
STEP 4 OF 5 · CONSTRUCTION MANAGER
GenStruc workflow · sample records · not AIManager accepts the new dates
Proposal accepted. The original dates are kept in the revision history with who accepted the change and when.
The recovery option stays pending until the plumber confirms.
STEP 5 OF 5 · AI
Homebuilding AI · in development, not yet verified · sample output2-week look-ahead · Lot 12
| Date | Task | Trade | Note |
|---|---|---|---|
| Nov 4–5 | Wall / Roof Sheathing | Framing | Resume when OSB arrives Wed |
| Nov 6 | Strapping | Framing | Ready after sheathing |
| Nov 9 | Strapping inspection | Inspector | Request now |
| Nov 10–11 | Wall / Roof Dry-In | Roofing | After inspection passes |
| Nov 12–13 | Plumbing Rough / Tubset | Plumbing | Nov 11 start if confirmed |
Result
A 2-day weather delay is pushed through the whole home schedule, with a recovery option and an updated look-ahead, before trades show up on the wrong day.
Related:Strapping inspection
Scripted sample: prewritten from this demo’s fictional records. No AI runs on these pages, and nothing is saved or sent. Labels: GenStruc workflow · sample records · not AI / Homebuilding AI · in development, not yet verified · sample output.
Home schedule
Fictional records| Task | Trade | Planned | Start | Complete | Status |
|---|---|---|---|---|---|
| Wall / Roof Sheathing | Framing | Nov 2–3 | Nov 2 | — | Started |
| Strapping | Framing | Nov 4 | — | — | Not started |
| Strapping inspection | Inspector | Nov 5 | — | — | Scheduled |
| Wall / Roof Dry-In | Roofing | Nov 6–9 | — | — | Not started |
| Plumbing Rough / Tubset | Plumbing | Nov 10–11 | — | — | Not started |
SELECTED CONTEXT
Wall / Roof Sheathing
Assigned trade: framing · Fictional assignment.
Example Start: Nov 2 · completion not yet recorded.
Milestone completion is not an inspection pass or occupancy approval.
Walk through a delayYOUR NEXT STEP